Mumbai  : On 17 November 2026, at 3:15 PM local time, Unit 1 of the Rooppur Nuclear Power Plant in Bangladesh was synchronised with the country’s national power grid. The Engineering Division of Rosatom State Corporation is the project’s general contractor and general designer. The first electricity generated by the plant was supplied to Bangladesh’s national grid. The reactor reached 40% of its rated power, while the generator output reached 370 MW.

“The power start-up of Unit 1 of the Rooppur NPP is a landmark event for our countries. Bangladesh is receiving a reliable, stable, and environmentally friendly energy source, which will significantly reduce its national energy dependence on imported hydrocarbons. Nuclear power provides Bangladesh with access to advanced technologies and contributes to the development of engineering and scientific research. For Russia and Rosatom, the power start-up of Unit 1 of the Bangladesh NPP is yet another completed project that demonstrates our country’s undisputed leadership in the global nuclear technology market,” said Alexey Likhachev, Director General of the Rosatom State Corporation.

In mid-October, Unit 1 was brought to its minimum controllable power level. This means a self-sustaining, controlled nuclear chain reaction is occurring in the reactor core.

The power startup phase involves a series of measures to gradually increase reactor power in several steps from 0% to a power level sufficient to start the turbine and synchronize the power unit with the grid (40% of nominal), ensuring the unit’s readiness for pilot operation. Once the reactor power reaches approximately 40% of nominal, the unit’s turbogenerator can be connected to the grid for the first time (since only at this power level can the unit’s steam generators generate enough steam to start the turbine and ensure its normal operation). This is followed by a lengthy period of gradual ramp-up to nominal power during the pilot operation phase of the new power unit, after which its commercial operation commences.

The implementation of the Rooppur NPP project contributes to strengthening Bangladesh’s energy security, developing its national energy infrastructure, and providing the country with a reliable source of clean electricity. The successful ramp-up of the first power unit to its minimum controllable power level is the result of the coordinated efforts of Russian and Bangladeshi specialists involved in implementing one of the country’s largest infrastructure projects.

****